A report about housing repairs statistics - less boring than it sounds

I've mentioned my role as Chair of Southwark's Housing Scrutiny committee a couple of times on this blog. Since taking this on in May last year our biggest piece of work has been an investigation into the statistics used to measure performance in Southwark's housing repairs service. Sounds technical, remote and boring doesn't it? I will do my best to convince you otherwise.

Back in July 2010, the committee had to decide which housing issues we wanted to look into. Councillors on the committee (from all parties) had just been through an election campaign in which we'd knocked on lots and lots of doors. Among Southwark's tenants, by far the biggest concern was the quality of the contracted-out repairs service.

But there was a problem. All of the statistics used to measure the quality of the service showed not just good, but brilliant levels of performance. 99.9% of appointments made by contractors were kept. Satisfaction levels hovered around the 94% mark. 90%+ of repairs were completed on time. Even more striking was the fact that, based on these stats, Southwark had won a national award for its repairs service from Inside Housing magazine, describing Southwark's repairs service as "the best in London".

Faced with these contradictory messages, we decided to try and do something different. Instead of doing a general scrutiny of the repairs service, we chose to investigate how the stats were gathered and calculated. Even the most cynical of the committee members could not have imagined what we would find. The stats were not just flawed, but rotten to the core. Just a few of the things we discovered were:

- most of the stats come from the contractor operatives themselves via mobile PDA devices. This means they completely control the information for each job they had been asked to do.

- concrete evidence of mis-reporting of the completion of work and attendance at appointments by contractors, found during a "case-tracking" process.

- satisfaction levels are measured with a survey which excludes anyone who has an ongoing problem with a repair.

- Satisfaction is measured with a five number rating system which is rarely explained to tenants doing a phone survey, and which is weighted in favour of higher levels of satisfaction.

- the results from a new (and reliably conducted) survey which show dramatically lower levels of satisfaction (69% compared to 88.4%), appointments kept (78.9% compared to 99.9%) than are shown in the official stats.

- contractors themselves admit their performance doesn't live up to anything like levels shown in the stats. One representative said: “I don’t recognise the performance of my operatives in these statistics.”

The report, which is still in draft form, concludes: “Southwark’s housing repairs Key Performance Indicators currently provide little or no insight into the actual quality of service being provided by SBS and Morrisons” It goes on to make constructive proposals for the creation of a system that can be relied upon, including:-

- A new texting system that will enable customers to verify if a call is complete via their mobile phone

- A satisfaction survey which accurately measures real levels of satisfaction with the repairs service

- a recommendation that the council makes sure it is no longer paying multiple times for single repairs. This will save the council money.

Through this scrutiny we found that the stats which have so often been wheeled out to prove how good Southwark’s repairs service is, are inaccurate and unreliable. For tenants this has meant unattended appointments and incomplete repairs going unnoticed. I hope this draft report will serve as a catalyst for improving the repairs service which too often lets down tenants in Southwark.

The draft version of the report can be found here from page 7 onwards: http://moderngov.southwarksites.com/mgConvert2Pdf.aspx?ID=4339&T=9

This will now be subject to some minor changes following last Tueday's meeting and will then go before the full Overview and Scrutiny Committee. The sub-committee is optimistic that the report will eventually go before Southwark Cabinet and the recommendations will be implemented.

Comments

  1. Well done Gavin. Any estimate of the cost of repairs paid for several times as in "a recommendation that the council makes sure it is not paying multiple times for single repairs"? Not possible to get the money back, I suppose. How about changing the contractors who do the repairs? (or don't do them).

    ReplyDelete

Post a Comment

Popular posts from this blog

Know Your Ryes!

A few weeks ago I was in a meeting with some local residents and council officers. During the meeting one person started referring to Rye Lane, when in fact they meant Peckham Rye East. Later on another started talking about Peckham Rye Common and it took us a little while to work out that they really meant Peckham Rye Park.   You can't really blame people for getting a little confused. There are so many references to "Rye" in our little bit of South London that even the locals can get mixed up. So I thought I'd have a go at writing a little glossary of all the Ryes hereabout.  Clearly I'm making a rod for my own back here, so please point out any errors I've made in the comments box below.  Anyway, here are my definitions of the ubiquitous Ryes. Some serious, some not so serious, and in no particular order: Peckham Rye Ward - The council ward area. Peckham Rye Ward was created out of Rye Ward, Waverley Ward and Bellenden Ward following the Local

Lib Dems claim they're not in charge in Peckham Rye

(A tweet from the Peckham Rye Lib Dems) Peckham Rye Lib Dems are now claiming that Labour 'run' Peckham Rye (take a look above). When asked by a local resident "Am I right in thinking Lib Dems run Southwark but Labour run Peckham Rye?", a Peckham Rye Lib Dem candiate replied, "Yes you're right. For the next three months Lab run Peckham Rye. Then we take over..." Given that, just like every other area in Southwark, Peckham Rye is run by the Lib Dem-Tory Executive it seems this is just the latest in a string of attempts to mislead people into thinking they've got nothing to do with Southwark's failures. Of course, Peckham Rye does have three Labour councillors, who do a great job of representing our area and our concerns at the Town Hall. However this is very different from 'running' Peckham Rye. If only we could just opt out of the Lib Dem chaos! In truth, the policy levers and almost all the money spent by the council are under the cont

Peckham Rye Adventure Playground: protected

As local residents will know, Southwark Council has suffered as a result of unprecedented cuts Government funding since 2010.  The council has had a third of its funding cut. As  a result  of these deep cuts, the council has been forced to consider reduc ing   adventure  play services.  This could have meant that Peckham Rye Adventure Playground, while keeping its weekend sessions, might have lost of its four after-school sessions . Many local people spoke to us about this issue and Renata, Victoria and I  were committed to using our local devolved budget to protect the hours to ensure the reduction would have been avoided. I’m very pleased to tell you that, at last night’s budget setting meeting, w e managed to secure a commitment that Peckham Rye Adventure Playground will see no change in opening hours.  We are now taking a look at how the hours are structured to see if it would be possible to open up the playground to more people over the whole of the weekend.  Watch thi